The Taber Waste Water Treatment Facility Bio-Reactor Project
EPCOR/Lockerbie & Hole
SCOPE
Flatwork
- Supply and install of rebar
- Form, place and finish flat pad
- Provide pumper trucks
- 3” keyway for water stop
Walls
- Supply and install of rebar
- Form, place, and finish walls
- Provide pumper trucks
- Install 10 lifting davit sockets
- Install 10 spools
Working Days -
Rebar -
Concrete -
Wall Height -
Rebar -
Concrete -
Wall Height -
Concrete -
Wall Height -
Wall Height -
51 working days on Octaform, 65 days total
87 ton
561 meters
17’2 to 22’4”